on 2015 Aug 12 7:51 PM
Hello SNP experts,
We are on SCM7 EHP2.
We use SNP heuristics for planning. We have a requirement where we want check the "Start of Lot size Grouping" by default when the Product comes into APO.
Is this a Config in APO or Should we use User-exit?
Please help.
Thanks,
SV
Request clarification before answering.
Hi Swathi
I have not cross-checked myself but you can first check whether lot size setting in ECC will populate the same. If not then you can check badi SMOD_APOCF005 and create implementation that while CIFing it can populate the same or you can check EXIT_SAPLCMAT_001.
Regards
Rahul