APO : Process order not sync between APO and ECC(Date and Time Mismatch)

0 Kudos
1,773

Hi All,

Process order not sync between APO and ECC(Date and Time Mismatch):

Below are the steps we followed and our observation below :

1. While Creating a Planned Order from /SAPAPO/RRP3 in the APO system.
2. Set the Conversion Indicator in the /SAPAPO/RRP4 for the Planned Order and save the Planned Order
3. Select the Converted Planned Order and change it into Process Order.
4. Process Order will be created by saving the results and we are seeing the discrepancy in the Availability Date and
Time between RRP3 in APO and MD04 in ECC.
5. These above steps is applicable for the Process Order in the Created state.
6. For the Process Order in the Released state , please flag the Order for release in the ECC system and the
same released status needs to be updated in the APO system.
7. We are seeing the difference in the Availability dates for the both Created and Released Process orders.

Note: Order is getting stuck in CCR and unable to reconcile the order eventhough there is no error queue and no error logs
captured in SLG1. Order is created in the time of the respective location. For few of the activities defined in the operation we could not see setup group in APO . One line Issue :Difference in the availability date and time of the process order in ECC and APO

Thanks,

Rajesh Kumar.

View Entire Topic
rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

There could be many reason of date and time difference between ECC and APO.

Do you have same issue if you convert order from ECC?

Do you have GR processing time ?

Execute T-code OX10 and check the time zone of the plant in R/3 system

Execute T-code /SAPAPO/LOC3 and check the time zone of the plant in APO system

Execute T-code CR03 and enter the work center of each operation, and check the factory calendar under the scheduling relevant capacity header

Execute T-code /SAPAPO/RES01 and enter the same work resource to check the factory calendar under the “General” tab

Please refer SAP note

2699668 - Delta report: daylight saving time causes false error 574 during operation start and end time comparison

And KBA on it

2208237 - CIF DELTA REPORT: error 161 for Manufacturing orders

Best Regards,

R.Brahmankar

0 Kudos

Hi Brahmankar,

, I have created process order and tried to change the date and time in APO and data is getting transferred from APO – ECC. In ECC I could see 5 records(With Recipes(5)) in CIF queue for each order. Record is getting updated based on latest date and time.

Now issue has been resolved.