Hi All,

There is a issue where extra alternative resources are coming with same Mode 'A' in PDS in APO. But in PV there is only one resource is maintained. No alternative resources are there. There has been no recent work center changes in ECC side. After retransfer of PV from ECC to APO, it got resolved. But user wants to know the root cause. Why alternative resources are there in PDS.

Thanks and Regards

Sumanta

Accepted Solutions (0)

Answers (1)

Answers (1)

p391977
Contributor
0 Kudos

Hi Sumanta,

Could you please check whether any material, resource or any related data change is done regarding the PDS in APO.

Also please check for the particular product-location how many PDSs are existing.

arsenal123
Explorer
0 Kudos

Hi Radheshyam,

Is there any t code through which we can see the changes done in PDS in APO? In APO for displaying PDS /SAPAPO/CURTO_SIMU is there. But don't know about the t code through which we can check change log history of PDS in APO. Can you suggest any t code for it?

Thanks and Regards,

Sumanta

p391977
Contributor
0 Kudos

To see any change log for an object, we can use transaction S_AUT10.