Hi, All,

IF we got a material BOM in SAP S/4 as below :

Header Material BOM for Finished goods :

Item no / Component / Alt grp

10 RAWA 01

10 RAWB 01

10 RAWC 01

20 RAWA 02

20 RAWC 02

In the alternative group 01, raw material A,B,C are in this group, component A is the primary component, could be replaced or substituted by component B and C

In the alternative group 02, raw material A,C are in this group, component A is the primary component, could be replaced or substituted only by component C

However, in the IBP Master Data Type Production Source item Sub

Only Key field Product ID

Source ID

Substitute Component Product ID

So does it means that in IBP, we can not have the alternative group concept like we have in the SAP S/4 ?

Or any alternative solution for this scenario ?