Actual Finish Date for Activity

Former Member
0 Likes
227

Hi,

I am interested to know which transaction I can use to generate list of actual finish date for process orders on a specific date.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

Hi Ruthvik,

Thanks for your comment.

I have tried that with actual finish date but what I really want was the actual finish date of a particular activity under operation. Are you able to guide me on this?

Ruthvik_Chowdary
SAP Champion
SAP Champion
0 Likes

Hi Eric,

Please Use COOISPI, scrool down you can find Actual Finished date