Hi, i need to show an activity (break activity, in other words pause time) in Gantt Chart. But in the standard activities there is no activity as 'break'. Is there any one who can help me?
In details: in the internal table ct_gnt_data_act there is no line for the activity break.
Is that possible to create a new kind of activity?
It is urgent.
Best regards.
Request clarification before answering.
Hi friends,
I have found the solution and would like to share it with you.
We have to append new lines to the view DD07V.
Then these new activities are available in SPRO and we can use them.
@Thanga You are right that i could be more precise 🙂 I'll try it my friend. Thanks for your reply.
Best regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.