Activation error Promotion level does not store data in days, weeks or months.

0 Likes
742

We are using a planning area based on unified planning area SAPIBP1, but have added the setup required for Promotions per SAP6/ Demand.

When all our configuration was standard- with Calendar Week as root in planning level, we got the error "Time-profile-level and Time-profile-level root for plan level CALWKPRODCUSTPROMO are not consistent".

To resolve this, we made Technical week as root in the plannig level

CALWKPRODCUSTPROMO. However, we now get the error "Promotion level CALWKPRODCUSTPROMO does not store data in days, weeks or months."

Is it a requirement to have Calendar Week as root in the Promotion Level of the planning area? If yes, how do we deal with the error:

"Time-profile-level and Time-profile-level root for plan level CALWKPRODCUSTPROMO are not consistent"

View Entire Topic
lingaiahvanam
SAP Champion
SAP Champion
0 Likes

Hi,

Can you share time profile and planning level screen shots to analyze this issue.

CALWKPRODCUSTPROMO should be at calendar week is root attribute.

Best Regards,

Lingaiah

0 Likes

Lingaiah, thanks for your reply. Yeah we had calendar week as root attribute in CALWKPRODCUSTPROMO, like it is in SAP6 planing area. However, we got the error

"Time-profile-level and Time-profile-level root for plan level CALWKPRODCUSTPROMO are not consistent".

What is the interpretation for this error? I am attaching the screenshot per your request, but it currently has Technical week as root.

Regards,

Shiva