2 CIF Getting created for planned Order Created APO

Former Member
0 Kudos
356

Hi,

When we create a planned order in APO we are getting 2 Que generated in R/3. One for creating the Planned Order and the Other for changing the Planned Order. Interesting factor is the 2nd Que which changes the Planned Order deletes the Negative Component. Can any one please let me know why is it first of all triggering 2 Que in R/3 (Create and change) rather it should be only one for create planned order.

Thanks & Regards,

Praveen.

Accepted Solutions (1)

Accepted Solutions (1)

former_member194106
Participant

Hi Praveen,

Could you please detail the steps that you are taking until the moment you see these 2 queues?

Are you first creating the order, saving it and after that changing it and saving the prod. view again? Or is it just the order creation that is triggering 2 queues to be created?

I would suggest to check the parameters maintained for the block sizes definition in APO (//CP3).

Thanks and regards,