Asset Strategy Performance Management (ASPM) took its first step with 1711 release and since then it has taken many steps forward. Being part of the ASPM development team I have seen its features enhancement with every release since 1711. ASPM is part of IAM portfolio -



In my blog series, I would like to share the step wise details of creating different kinds of assessment in ASPM. The details will be based on 2005 release.


Series 1: Brief Overview of ASPM and Master data setup


Series 2: Risk and Criticality (RC)


Series 3: Failure Mode Effect Analysis (FMEA)


Series 4: Checklist Assessment


Series 5: Reliability Centered Maintenance (RCM)


Series 6: Recommendation

Series 7: Preventive Maintenance Review (PMR)


There are multiple blogs available on ASPM product and its features, hence in this blog series I will be focusing on the activities which the reliability engineer and maintenance planner would do using ASPM.


On a high level, ASPM provides a well-integrated solution where in, as a reliability engineer you can perform set of assessments on the asset to recommend a maintenance strategy. With its integration with other Intelligent Asset Management (IAM) products and SAP PM, reliability engineer gets a complete 360* view of the asset which helps in taking an informed decision on what kind of maintenance strategy would be appropriate for the asset. For the maintenance planner, ASPM provides a complete information on all the recommendation which are provided by the reliability engineer. The maintenance planner can further enhance the maintenance strategy and execute them.



Process Overview:



Based on the technical breakdown of assets (example: Equipment) users can first perform a Risk & Criticality assessment of all the assets. In a matrix, they can rate probability and consequence of failure in various categories. Out of this exercise, assets are classified in different criticality and the reliability engineer can decide what should be the next actions like RCM/FMEA assessments. In case of assets with a lower criticality, the decision might result in a run-to-failure approach or following the manufacturer’s instructions set, which is being provided through SAP Asset Intelligence Network. For medium-critical assets, a review of the existing maintenance plans and task lists is recommended. New maintenance intervals can be calculated based on historic failure data. For the assets with a criticality above a certain threshold, the solution provides capabilities for performing an FMEA and RCM. With its ERP integration, user can view the maintenance plans and task list created in ERP and further enhance it by providing recommendations. A general term for continuous cycle of improvement is PDCA.

  • Plan - establish the objectives and processes necessary to deliver results in accordance with the specifications

  • Do - Asses the asset to complete the analysis

  • Check - monitor and evaluate the processes and results against objectives and specifications and report the outcome

  • Act - apply actions to the outcome for necessary improvement. This means reviewing all previous steps and modifying the process to improve it before its next implementation


The PDCA can be completely mapped with IAM portfolio as mentioned below -

  1. Plan step is  where the ASPM supports with different kinds of assessment - RCM / FMEA / Checklists

  2. Do step is where planned maintenance gets involved via MP, Tasklists,  Notifications and WO

  3. Check step is where different kinds of analysis can be done via PdMS and SAC

  4. Act step is  again where ASPM  comes in in forms of re-assessment and RCA processes(planned scope)



The ASPM solution overview is defined with six steps. The Define to Verify cycle can also be mapped to the PDCA cycle -




  1. Define & Identify  -  This is the "plan" phase in which asset information is defined and criticality assessment is done on the asset which gives the strategy on how to further asses the asset if there are critical

  2. Analyse &Recommend - This is the "do" phase in which detailed assessment are done to arrive at a set of recommendation

  3. Implement - This is the "act" phase in which the previously identified recommendation are implemented.

  4. Verify - An finally the entire process is monitored to ensure the process is helping in continuously improving the asset.


I will start with the step 1 of defining the asset information.


The below master will be considered for the assessment:




  1. Model Template – “Centrifugal Pump Template” with subclass as “Centrifugal”

  2. Model: “Centrifugal Pump” created from model template “Centrifugal Pump Template”

  3. Equipment Template: “Fire Fighting Equipment Template” containing local indicators

  4. Equipment Template: “Dewatering Equipment Template” containing asset indicators which gets updated after risk & criticality assessment and FMEA assessment

  5. Equipment: “Fire Fighting Pump” created from “Fire Fighting Equipment Template “ and “Centrifugal Pump” model.


The below information is created in the respective master data(Functions/Functional Failure/Failure Mode/Cause/Effect) which will be used during our assessment to create the below hierarchy for the equipment:

  1. Equipment: “Dewatering Pump” created from “Dewatering Equipment Template” and ““Centrifugal Pump” model.


The below information is created in the respective master data(Functions/Functional Failure/Failure Mode/Cause/Effect) which will be used during our assessment to create the below hierarchy for the equipment: In the next blog I will provide details on performing risk and criticality assessment on the equipment created namely “Dewatering Pump” & “Fire Fighting Pump”.















































Full Text Abbreviation
Asset Strategy Performance Management ASPM
Risk and Criticality RC
Failure Mode Effect Analysis FMEA
Reliability Centered Maintenance RCM
Preventive Maintenance Review PMR
Fiori Launch Pad FLP
Function FN
Functional Failure FF
Failure Mode FM
Risk Priority Number RPN

Further Links


SAP Help Portal

21 Comments
0 Kudos
Thanks for sharing rupali.ray
This captures the required steps in great detail.

Thanks and Regards,
Arush
former_member688897
Participant
0 Kudos
Hello Team,

Do we have a functionality to capture Warranty Information in AIN Equipment/Model which would flow back to S4 Equipment as Vendor Warranty Start and End dates? E.g a manufacturer provides a 1 year warranty on a new equipment of a specific model and wants to publish the same for a specific set of operators/customers?
rupali_ray
Employee
Employee
0 Kudos
Hi Gaurav,

No currently warranty information is not captured in in AIN equipment/model
former_member688897
Participant
Thank you.

Is there a blog available on using the Failure Mode analytics model management and its prerequisites as well using machine learning.
jeyaspursuit
Explorer
0 Kudos
Hi , can we know how SAC helps in analysis with respect to ASPM functionality

Thanks

Jey
former_member688897
Participant
0 Kudos
If the equipment is disposed off or retired, is there any control which forbids doing any further assessments like FMEA on the same Equipment?

Thanks
rupali_ray
Employee
Employee
0 Kudos
Right now, assessment is allowed in any published/inrevision equipment/asset.
rupali_ray
Employee
Employee
navdeep786
Explorer
0 Kudos
Hi Rupali,

Many thanks for such an informative blog. What I could understand from my ASPM system that it is not possible to create Classes and Sub-classes in ASPM module and the same is with their templates. Is it correct or am I missing something? Since we are not planning to use Asset Integration Network, then how would I bring my existing Class and subclasses to ASPM system?

Best Regards,
Navdeep

 

 
rupali_ray
Employee
Employee
Class/subclass are delivered by the foundation layer, hence you will get it in ASPM system even if you dont have AIN. Regarding templates, I assume you are referring to equipment/location/etc template. Those can be created by end user.
navdeep786
Explorer
0 Kudos
Hi Rupali,

Ok, I will check in the Asset Central Foundation. And by template, I meant the template for Classes and Sub-Classes in ASPM solution.

Best Regards
rupali_ray
Employee
Employee
0 Kudos
Templates to create class/subclass not available. You can create template only for Model/Equipment/Location/Spare Parts/System/Functional Location.
former_member688897
Participant
0 Kudos
Hello Rupali, For defining the failure modes and patterns currently we understand that its a manual way to choose the respective graphs for a failure pattern. Is there a flexibility within ASPM to have an interface with any third party system(Non cloud) where these patterns are generated and we can then sync the failure modes and type of graph from that system?
rupali_ray
Employee
Employee
0 Kudos
You can consume public FM APIs to update the fields.
former_member688897
Participant
0 Kudos
Hello -

The /ACI/TEMPLATE_MAPPING is not displaying the class of  type 002 created in S4,what could be the reason? We want to link the Model Templates to our class created in S4
former_member688897
Participant
0 Kudos
Hello Rupali,

In order to load new equipment's data in S4 lets say a volume>10000 we can load via mass programs in S4 like LSMW to a point where equipment and its classification can be loaded and Equipment  would get replicated to AIN. In order to link it in the AIN further with data such as Indicators, Alerts,Failure modes we would then need to build some additional custom programs using the API's provided? Is this understanding correct or is there some other provision as well?
murali1254
Product and Topic Expert
Product and Topic Expert
0 Kudos
Dear Gaurav,

You can upload >10000 equipment's into the cloud system using your mass program or standard sap provides a concept called an initial load, by using this you can easily upload all the collection of equipment. But you need to implement enhancement to sync Indicator, alert, and Failure modes into the cloud system. Please go through the below link for more information.

 

https://help.sap.com/viewer/f90a444330144d5db63d345e298b5cff/2102/en-US

Regards

Murali Saripalli

 
murali1254
Product and Topic Expert
Product and Topic Expert
0 Kudos
Dear Gaurav,

Please select Equipment from the dropdown after executing the template mapping program, so that it displays all the irrespective of equipment classification types as part of sap we provided 002 is equipment class type if you have your own /custom Equipment types and if any classes have been created with the same type, those classes also will appear here.

FYI, you should not link equipment classes with the Model template. we are not supporting it. hence it won't work.

But Material classes can be linked with Model templates.

 


 

Regards

Murali

Equipment Templates

former_member688897
Participant
0 Kudos
Thankyou. For the comment "you need to implement enhancement to sync Indicator, alert, and Failure modes into the cloud system."-

Since these objects are not linked to any S4 master data objects we assume that we would need to load these via some flat file from S4 and then build enhancement to sync the indicators etc.

Does initial load provide a mechanism to load via a Flat File from S4?

Is there any future road map to have some standard  programs available to load the data directly in AIN?
murali1254
Product and Topic Expert
Product and Topic Expert
0 Kudos
sorry, we are not supporting the flat-file approach.
former_member688897
Participant
0 Kudos
Thankyou. Another clarification on the point above   "you should not link equipment classes with the Model template. we are not supporting it. hence it won't work."

Does this mean we cannot sync the attributes from AIN to S4 Equipment classification either directly or even while doing checklist assessment?. Is this functionality going to be available in the future or would never be supported?