Supply Chain Management Blogs by Members
Learn about SAP SCM software from firsthand experiences of community members. Share your own post and join the conversation about supply chain management.
cancel
Showing results for 
Search instead for 
Did you mean: 
Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
7,873

Multi Resource Scheduling Heuristics in S/4 HANA


Purpose:
The purpose of this document is, How to reduce the total lead time of the multiple Orders loaded on the same Resource, with the same Start Date using the most suitable Heuristics in PPDS. You can use this algorithm(FM: /SAPAPO/HEU_MULTIRES_SCHED) to switch modes and sources of supply according to defined time blocks, to keep the receipts as close to the required date as possible.
Configuration Data
Activate the Business function
Using the Transaction: SFW5, Need to activate the below Business function SCM_APO_PPDS_PI Copy the Multi Resource Heuristics Create Master Data
The below scenario is based on the Master data Finished Material: PPDSFIN1 Raw Materials: PPDSR1 & PPDS R2. Create BOM for the Finished material : PPDSFIN1
Work Centres: PPDSWC1, PPDSWC2, PPDSWC3 (Maintained as Modes in PDS) .
Create Routing for the FG Material, with Operation details maintained with Classification.
Create the Production Version Creation Product Data structure
Create Material Master
Material Master for all the required Materials like, FG, & Raw Materials can be created using Transaction Code: MM01. Make sure, for these Materials Advanced Planning Check, activated & necessary filed values maintained in the Advanced Planning.
Create BOM
Follow standard steps for creating BOM for the FG Material using the T Code: CS01
Create the Work Centres using the T Code CR01
Activate the Advanced Planning & also maintain the APO Resource Settings.
Maintain the Classification, for Identifying the Alternate Resources


Maintain the same for all the rest of the alternate Resources like PPDSWC2   & PPDSWC3
Create the Routing using the T Code CA01
Follow the standard stapes to create the Routing for the FG Material
Maintain the Classification at the Operation Level, with Class Type: 19 & assign the Class as shown below, with Priority as the Characteristic



Create Production Version
Follow the standard steps for creating the Production Version
Production Version is nothing but the Combination of BOM & Routing


Create Production Data Structure
T Code: CURTOADV_CREATE
Create the Production Data Structure for the Finished Product in the Plant 1710
Once created the Production Data Structure, you can view/display the same using the
T Code: /SAPAPO/CURTO_SIMU (For the Finished Material: PPDSFIN1)*** Make sure, all the Alternate Resources data is visible in the Modes
Execute the below Transaction Steps
Create the Planned Orders in the Product View of the FG Material
Using the T Code: /SAPAPO/RRP3.
Create Multiple Planned orders, with same Start/Completion Date & with the smaller Lot size to get completed within the Day (Each order will take Less than 8H)
Take a look of the below Example, Planned Order with Order Qty : 4 are created with the same Start/Completion Date**Make sure, all the Orders have the smaller Lot sizes
Execute the Heuristics I the Detailed Scheduling Board.
T Code : /SAPAPO/CDPS0
Maintain the Heuristic Profile in the Profile details

Look at this Video, to visualize the Effect of the Multi Resource Scheduling Heuristics



Hope this helps You in understanding the Concept of Multi Resource Scheduling.
Thanks A Lot for all Your kind feedback/comments.
Best Regards : Raja Sekhara Reddy Bannuru

Useful Links : https://wiki.scn.sap.com/wiki/display/SCM/Scenario+-+Run+Heuristic+SAP_MULT_SCH+in+PPDS+Planning+Boa...
4 Comments
Labels in this area