Introduction:
EWM and PP process integration enables the consumption of raw materials for production and
the receipt of finished goods back into the warehouse.

Workflow:

  • The process is initiated with the creation of a Production Order or Process Order in the S/4HANA system. Subsequently, in the EWM system, components are picked against the production order and staged in the Production Supply Area (PSA).
  • These components are then consumed at the work center during the manufacturing process to produce the finished goods.
  • Key master data elements such as Work Center, Bill of Materials (BOM), and Routing play a critical role in this process.
  • The process can be further designed to route the finished products back to the warehouse using an Inbound Delivery from production.
  • Additionally, a Quality Inspection step can be incorporated through POSC before the finished goods are moved to their final Putaway bins, ensuring product quality and compliance.

GowthamParasa_0-1744142344596.png

GowthamParasa_1-1744142428949.png

GowthamParasa_2-1744142507366.png

 

                                   Differences between Production Order and Process Order:

GowthamParasa_4-1744142729213.png

                        Advance Production Planning integrates with EWM has two Steps:

  • Consumption of Raw Materials.
  • Receiving of Finished Products

                                   1.1 Consumption of Raw Materials:

                                                      Configuration:

GowthamParasa_5-1744142889767.png

 

GowthamParasa_6-1744142986019.png

GowthamParasa_7-1744143077635.png

GowthamParasa_8-1744143111327.png

GowthamParasa_9-1744143168163.png

GowthamParasa_10-1744143208724.png

GowthamParasa_11-1744143264640.png

GowthamParasa_12-1744143301342.png

 

GowthamParasa_13-1744143338543.png

GowthamParasa_14-1744143430580.png

                                                     Production Planning Master Data

GowthamParasa_15-1744143536706.png

GowthamParasa_16-1744143573669.png

GowthamParasa_17-1744143623627.png

 

GowthamParasa_18-1744143659242.png

GowthamParasa_19-1744143691461.png

GowthamParasa_20-1744143746192.png

GowthamParasa_21-1744143800719.png

 

GowthamParasa_22-1744143832366.png

GowthamParasa_23-1744143886143.png

 

GowthamParasa_24-1744143969559.png

 

GowthamParasa_25-1744144020541.png

                                                        Material Master Settings

GowthamParasa_26-1744144108935.png

GowthamParasa_27-1744144199023.png

GowthamParasa_28-1744144233101.png

GowthamParasa_29-1744144274659.png

GowthamParasa_30-1744144372823.png

 

GowthamParasa_31-1744144417291.png

GowthamParasa_32-1744144484742.png

GowthamParasa_33-1744144527492.png

GowthamParasa_34-1744144615745.png

GowthamParasa_35-1744144671367.png

GowthamParasa_36-1744144712707.png

GowthamParasa_37-1744144750525.png

GowthamParasa_38-1744144802741.png

                                                                Testing:

GowthamParasa_39-1744144856378.png

GowthamParasa_40-1744144899837.png

GowthamParasa_41-1744144927079.png

GowthamParasa_42-1744144971600.png

GowthamParasa_43-1744145016596.png

GowthamParasa_44-1744145058556.png

GowthamParasa_45-1744145109628.png

GowthamParasa_46-1744145162764.png

GowthamParasa_47-1744145251041.png

GowthamParasa_48-1744145277538.png

GowthamParasa_49-1744145302066.png

 

GowthamParasa_50-1744145327698.png

GowthamParasa_51-1744145370997.png

GowthamParasa_52-1744145401149.png

GowthamParasa_53-1744145429897.png

GowthamParasa_54-1744145475420.png

GowthamParasa_55-1744145525651.png

GowthamParasa_56-1744145566570.png

GowthamParasa_57-1744145661198.png

GowthamParasa_58-1744145690656.png

GowthamParasa_59-1744145724537.png

GowthamParasa_60-1744145777027.png

GowthamParasa_61-1744145835038.png

GowthamParasa_62-1744145876980.png

GowthamParasa_63-1744145925868.png

GowthamParasa_64-1744145979566.png

GowthamParasa_65-1744146004584.png

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3 Comments
schulte-bahrenberg
Contributor
0 Kudos

Hi Gowtham, 

thanks for the comprehensive summary. One question - 

Why are your raw materials already in P2 stock type ahead of creation and confirmation of the staging WTs? My understanding is that you've maintained stock determination rules to allow picking from F2 and avoid having to post to P2 upfront (or store as P2).

Regards, 

Hendrik

GowthamParasa
Participant

Hello @schulte-bahrenberg 

Thanks for bringing this up — your observation is absolutely valid.

Ideally, with the stock determination strategy configured to pick from F2, the system should consume directly from unrestricted-use stock without requiring materials to be posted into P2 upfront.

However, in this specific scenario, the raw materials were already posted to P2 due to upstream planning decisions. As a result, the system simply utilized the stock that was already available in P2 at the time of staging. Once the P2 stock is consumed and reaches the final destination (e.g., after staging or goods receipt), it is converted or posted into F2 , So the behavior observed aligns with system logic.

Appreciate your insights — always helpful to align on the intent vs. actual flow.

Best,
GowthamParasa

schulte-bahrenberg
Contributor

...thanks for clarifying @GowthamParasa ! Got your point!