on 2009 Oct 21 12:11 PM
Hi SRM Gurus,
I am using SRM 5.5 with Extended Classic Scenario and Plan Driven Procurement(PDP).
My question is: I was unable to create PO with reference PR/RFQ/Manually in R/3.System is giving an error message 'you can order locally(SRM)'. Which material group and Purchasing groups are maintained in PDP table. If I delete this entry I can Order PO in R/3.
Now I don't want to delete PDP table entry and I want to Order PO in R/3. How can I do it?.
Please focuses light on this issue. Highly appreciate.
Regards,
John.
Request clarification before answering.
Hi,
Try resetting the profile indicator once the PR is transferred to the SRM system in the BADI BBP_BADI_EXTREQ_OUT in R/3.
BR,
Deepti.