Without delete PDP table entry, I want to Order PO in R/3. How can I do it?

Former Member
0 Kudos
325

Hi SRM Gurus,

I am using SRM 5.5 with Extended Classic Scenario and Plan Driven Procurement(PDP).

My question is: I was unable to create PO with reference PR/RFQ/Manually in R/3.System is giving an error message 'you can order locally(SRM)'. Which material group and Purchasing groups are maintained in PDP table. If I delete this entry I can Order PO in R/3.

Now I don't want to delete PDP table entry and I want to Order PO in R/3. How can I do it?.

Please focuses light on this issue. Highly appreciate.

Regards,

John.

View Entire Topic
Former Member
0 Kudos

Hi,

Try resetting the profile indicator once the PR is transferred to the SRM system in the BADI BBP_BADI_EXTREQ_OUT in R/3.

BR,

Deepti.