Why Confirmation not updated in ERP

Former Member
0 Likes
186

Hi All;

We are using SRM 7.0 classic scenario & ECC6.

The user created confirmation and the manager approved it. but while transferring to backend, somebody was editing the PO. As a result, the system did not update the GR in ERP.

When i checked in in BBP_PD i found stats: currently being transferred"

How can I trigger again the confirmation to be transferred to backend.?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

Hi

If the IDOC for confirmation is stuck then find the failed IDOC in WE05 and try to re-process the same in BD87 in SRM system.

with regards

Manjunath

Former Member
0 Likes

Dear;

I have already checked in WE05 but I dod not find that IDoc other IDocs are successfull.

Now I am trying to cancel or re-confirm the confirmation but the system gives error message

System status FREE is active

System Status TRANS is active

what should I do to re-transmit it.

Former Member
0 Likes

Have you maintained appropriate message type in WE20?

Regards,

Nikhil