on 2021 Jul 06 1:20 PM
Hello Team,
We are implementing ARIBA Sourcing.
The Client wants to ensure that there is a strict control when event timings are extended and reduced by Project Owner. Currently, there is no approval or workflow triggered
Ideal requirement is to have all time changes approved by Manager before it can re-published.
However, from the documentation, I do not see any approval process straight forward.
Would love to hear if there are any workaround.
Also, even-though the user is a "Junior Sourcing Agent", as he becomes a project owner while creating Sourcing Project, he is able to extend time without any approvals. if there can be any restriction setup at the project owner side as well so that only Sourcing Agent/ Sourcing Manager has the ability to extend time.
Request clarification before answering.
Project Owners and Users assigned with the Event Administrator role in the event will always be able to reopen, extend, and reduce timing of the event.
However, the option of setting the Publish Approval task originating from the template of the event can require Junior Sourcing Agents to follow a review workflow before republishing an active event with changes.You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.