on 2010 Jan 18 6:18 AM
Hi,
One user has created a shopping cart and a PO has been crerated in the backend system.
After this the requester of the shopping cart has left the organization and delinked from the Org structure.
What should i do to post confirmations for that shopping cart?
I have a user with central recipient rold but still he is not able to post confirmations wrt to the SC.
Please let me know if there is any other possible solution for this scenario.
Regards,
Vignesh
Request clarification before answering.
Hi,
Goods Receipt can be created in MM side as workaround.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Vignesh,
In order to confirm your PO, re-assign user concerned to his initial position and his position to his initial organizational unit.
In this way, PO Goods Recipient partner will be linked again to its initial user: this will avoid current error you have got in your PO. So, confirmation will be then allowed with any central recipient.
Regards.
Laurent.