on 2010 Aug 04 11:24 AM
Hello:
We are running an scenario to transfer a SC from cProjects (xRPM 4.5) to SRM 7.0. The use of XI is mandatory. Basically, we work with a project in cProjects and we would like to create a material/external request that must be transferred to SRM as a SC.
Our issue is that we are not able to create the SC in SRM. The status of the SC in cProjects is "In Preparation" which means that the information is not received in SRM to create it. We are almost sure that no technical issues exists. We assume that there is some relationship between the Organizational Structure in SRM and the account assignment associated (WBS element of the project) to the requirement in cProject. Another possibility is that the system user which performs the information transfer has not the correct profiles and authorizations
Does anybody has faced a similar problem? Many thanks.
Francisco
Request clarification before answering.
Hi,
Please check the PI user is in SRM Org structure. What is the message status in SXMB_MONI transaction?
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Masa:
The message is OBJECT_ID_NOT_FOUND. The user of XI has been created in the SRM Org. Structure as an employee. It has the autorizations SAP_ALL, SAP_EC_BBP_ADMINSITRATOR and SAP SRM Administrator. I think that are two possbilities:
a) XI user needs other authorizations
b) Something is missing in the Org. Structure (Attribute, role, etc.).
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.