on 2012 Nov 22 1:16 PM
Hi All
When I was trying for initial download of materials in our Quality system I met with the above error in SMQ1 in SRM stating 'The current application triggered a termination with a short dump' .
When I checked the dump in R/3 it said, CRMATAB is empty, it must be filled.
But I checked the same table in our production system and it is empty there too. And in production systems I could replicate the materials without any errors.
I have checked all the settings of Quality system with that of Production systems and there is no difference.
I have checked numerous notes and threads as well. But couldn't find a relevant information.
Anyone please suggest why is this error only in Quality system?
Request clarification before answering.
Hi Dhananjay,
Please refer to oss note 1498111. This should resolve your issue.
Thanks,
DT K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi DTK
Thank you so much for your reply and apologies for delayed response. Was too busy at work
I checked this note and yes, i guess this is feasible for me. Only problem is my SP level of PI-BASIS component. I guess i can somehow work it out.
But my question is, every setting, including CRMATAB table are exactly same in Prod and Acceptance environments. (both the environments, CRMATAB in r/3 and SRM are empty)Queue runs in Production but doesn't in Acceptance.
I am just trying to figure out what could be the reason for this failure in Acceptance system.
I hope you can help me.
Thank you so much
Dhana