Hi Gurus,

I'm working with SRM 7 abd I would need some information about how to setthe the flag PERMIT PROXY BIDDING as default for all the new suppliers/bidders that will be created.

Thanks in advance for your support.

Best Regards,

Valentino

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes

Hi

You will have to click on the indicator for Allowing Proxy bidding when the Bid Invitation is created by the Buyer before publishing it to the Bidders. This is a standard feature and not additional configuration is required for this.

Regards

Virender Singh

Former Member
0 Likes

Hi

Regarding your default setting of the indicator in All Bidders/ suppliers, I dont think that is delivered as a part of standard functionality. You will need to ensure it as a part of your Vendor Onboarding process or have something custom functionality build around the same