Schedule the Report "BBP_EXTREQ_TRANSFER" in ECC system.
This report is scheduled in background to pick up requisitions from EPRTRANS table and push it to SRM.
Br,
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
if you want to use the new SRM 7.0 scenario check note
1263876 - SAP SRM: Configuration of Procure-to-Pay Scenario
Regards
Stefan
Hi BS
Please find below the links .. its pretty straight forward .
1. Create a PR
2. Release the PR
3. Run the report BBP_EXTREQ_transfer
4. Check nothing stuck in Queues SMQ1 , SMQ2 etc ..
For more understanding and configuration refer guides below
http://scn.sap.com/docs/DOC-2721
1263876 - SAP SRM: Configuration of Procure-to-Pay Scenario
http://help.sap.com/saphelp_srm40/helpdata/en/99/8afc524b07574fa215b32f1da9ddd4/content.htm |
Regards
Vinita