on 2011 Jun 16 6:06 AM
HI Everyone,
We are using Classic Approach and the SRM is integrated with ECC. Now we have a problem after doing client copy. We have done client copy only for Quality from PRD in ECC and not for SRM PRD to quality. So there is no proper sync between the SRM Quality and ECC quality. Hence the integration is not proper and the documents are not generated in the ECC quality.
Please guide me the procedure of how to sync the ECC with SRM qualtiy.
Thanks.
Siva
Request clarification before answering.
When system is copied from other systems all Logical systems and RFCs will be pointing to the old system. You need to run T-code BDLS for changing the Logical systems to the current systems. Then delete all master data like Material groups, Materials master, Vendors and then re replicate. This should solve your issue.
Thanks,
Jagadish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.