on 2016 Feb 05 10:23 PM
We are using SRM 7.1 SP9
Scenario: SC: 100Qty PO: 100Qty
Sourcing relevance indicator on SC: Blank
PO Qty reduce to 95
5 Qty show up in sourcing.
Buyer reject it
Sourcing relevance indicator on SC: Y ...
PO Qty reduce to 90
SC not showing up in sourcing and Sourcing relevance indicator remain Y ...
Is it SAP Std. or Bug
Please assist.
Regards
Sandeep
Request clarification before answering.
Hi Sandeep,
This is a standard behavior.
Once the SC item is rejected in soco, sourcing flag will be set to 'Y" to the item. And system considers its sourcing completed already by purchaser and will not send it back to soco even though you reduced again the quantity of the follow-on PO.
Best regards,
Wendy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In addition to this type of issue,I have one more issue
My client has extended classic scenario,
SC created with 8 line items-->approved and PO created for all the line items but few of the line items are showing it is as In purchaser's worklist.
I can run the FM and I can remove the source_REL indicator to empty .But any guesses on the reason why it happened only for specific line items ?
can you explain me on this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.