Hello Gurus,

We have a PO with single line item. User cancelled the PO from SRM portal.

Now the issue is PO is in awaiting approval status, after executing the FM "BBP_PD_PO_TRANSFER_EXEC" status on PO changed to Error in process.

When I click "Check" button on PO, getting below error because we dont have a backend PO with this number (Found No PO in ECC)

How to change the PO status to cancelled ?? Can someone help us to resolve this issue??

Thanks in advance.

View Entire Topic
Former Member
0 Likes

Hi Sanjay

You can do a dummy change and add a new item or delete the PO item as Summer mentioned

If you are not able to do any of this can you refer note as below and see if this is the issue you are facing?

1046593 - Limit PO - Unable to delete and create new item

I am assuming you are using SAP SRM extended classic functionality .

Regards

Vinita