We implemented SRM7.0 Extended Scenarion on Jul 1 , 2011. We have an issue with ECC 6.0 work order requisitions transfer to SRM system. About 2 0f 10 requisitions creetd in ECC are not transferring to SRM. Sometimes user created 20-30 requsitions and tehy faile to transfer immediately as configured. Then about a day or week later some the requisitions transfers to SRM but some remain in limbo. SRM system do not issue an erro message. We run post processing desktop (\SAPPO\PPO2) to see why requsitions did not transfer. This program doe snot pick up the requisitions that are in limbo or pending status.

Any ideas why transfer is not consistent.....

View Entire Topic
former_member22425
Active Participant
0 Likes

Hello,

Check for the PR Release Date in the Item details under the tab Quantities/Dates for the PR your are transferring here.

Try with the nearby release date the reported scenario should work fine.

Best regards,