on 2013 Jul 26 4:24 AM
Dear Experts,
1 - Is it possible to use parallel worklow in the Process Controlled Workflow for BUS2201?
I need to send all approvers (cost center) a work item in parallel instead of one after the other in a fixed sequence.
2 - For the Shopping Cart (BUS2121) there is a implementation /SAPSRM/BD_WF_SC_RR_PA.
Is there any standard implementation for BUS2201?
Regards,
Alexandre.
Request clarification before answering.
Hi,
Parallel Approval is available from SRM 7.0 EHP1.
You need to activate an irreversible switch first to use this functionality.
for more information:Check this
http://help.sap.com/saphelp_srm702/helpdata/EN/c9/e6c2d976564cfe83ba850890d6f946/content.htm
Agent Determination - SAP Documentation
Regards,
Ashish