on 2010 Jul 06 12:48 PM
Hello,
We are able to successfully create the below scenario.
PR in ECC --> Get PR in SRM --> Start Collective processing -> Transfer to Central System (SC is created for the PR @ this time) --> Create RFx --> Rfx Response --> Create PO. (PO is created in ERP, Classic Scenario)
We are able to get the PR & we are able to create SC successfully and the PR/ SC is available in Sourcing cocpit.
Able to create RFx --> Rfx Response.
Now once the RFx Response is Accepted --> We go for creating PO.
Classic Scenario.
The error is due to pricing - debugged and checked as mentioned in my earlier message.
IPC pricing is switched off and the BADI for simple pricing is activated.
Error : " Message A BBP_PD 396 cannot be processed in plugin mode HTTP "
But this is due to pricing is what i guess.
Error is raised in FM "BBP_PDPRC_UPDATE".
Kindly Suggest.
Regards.
Edited by: Purshothaman P on Jul 6, 2010 1:50 PM
Request clarification before answering.
Hi Purushotoman
I am using Classic scenario with ERP EHP4 and SRM7.0
Trying to send the ERP-PR with attachment in header level/item level to SRM SC.
But file attachments are not recieved at SRM SC. are you getting both header and item level attachments sent by ERP PR.
can you please give your response...i am struck up here.
Regards
Chandra