on 2009 Dec 27 10:08 AM
Hi All,
I need to setup a SRM Systems for our internal training purpose
SRM 5.0 and SRM 7.0
Can I use one back-end (ECC6) for both the servers (SRM 5.0 and SRM 7.0)
Is there any issue
Thx
Jai
Request clarification before answering.
Hi,
I have never done it, but I guess that could be feasible.
Pay special attentions to several points:
Document Range Number. Define different Ranges, otherwise you are going to overlap documents and mix processes.
Define all the partner profiles, Logical systems and so on..
Define all the RFC destinations.
u2026u2026
Thanks and Regards,
Abraham