on 2006 Dec 20 11:00 AM
We have created a contract in SRM5.0 for backend service & local(SRM) service
Source is getting determined for local(SRM) service while creating shopping cart/request.
<b>But source is not getting determined for backend (R/3 ECC6.0) service replicated in SRM while creating request/SC.</b>
Kindly suggest.
Rgds,
NNK
Request clarification before answering.
Hi,
Which scenario are you using ? classic ? ECS ? local ?
If ECS or local scenario, ONLY local source of supply is being search by the system .
Thus no backend SOS is searched for these scenario.
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yann
We are using de-coupled scenario (PO's for R/3 materials are created in R/3 AND PO's for local material are created in SRM).
We have used different product categories for R/3 & SRM.
Everthing is working fine for materials.
But for R/3 services we are facing this problem.
For SRM services everthing is fine.
Rgds,
NNK