How do we know , whether the SC in SRM is converting to PR or PO in ECC.
any Badi's needs to be implemented , i have checked BBP_CREATE_BE_RQ_NEW(SRM)
BAPI_PO_CREATE1(ECC) but dint understand.
please gudie me
Regards
Srinivas
Request clarification before answering.
HI ,
I have seen the follow on document settings in SPRO,
SRM server- BADI-Follow on Doc Generation in Backend--PO Backend
PR backend
Both are implemented in my system...its like for PR it is BBP_CREATE_BE_RQ_NEW and PO it is BBP_CREATE_BE_PO_NEW
so would like to know which one will create after SC completion..
Regards
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivas,
You dont have to go to Badi Section , go to below path in SPRO and check
SPRO ->IMG->Supplier relationship management ->SRM server-> Cross Application basic settings-> Define Object in Backend System (Purch.Reqs, Reservation, Purch.orders) and you will understand what is configured.
Ideally if the shopping cart is complete like it has fixed vendor price etc , it will create PO for incomplete SC it will create PR.
Thanks