Hi ,
We are in SAP SRM 7.13 Version: Extended classic scenario
We are configured PDP scenario and we transfer the PR through RFC program and BBP_EXTREQ_TRANS.
For materials PR we have no issue but for the Service PR’s we are getting the issue(not transferring to SRM) and SLG1 log says the below errors.
Error message: Not Possible to calculate tax
Error message: Error in parameter transfer
Stop: No logical system for FI is maintained; inform system admin.
Stop: Enter the company code
Error message: Enter product category
Error message: Enter Quantity
Enter unit of measure
Stop: Document type for determined back-end system missing
Warning message: Enter a value in the mandatory field commitment item in account assignment
Note we have only one company code and we don’t have any issue during material PR transfer.
Regards,
Anjan Sayana
Request clarification before answering.
Hi,
First I suggest you check the following KBAs:
1915491- Settings for the RFC user for External requirements in SRM
1646982 - How to enable external requirement transferThen please make sure all the data in ECC PR are already mapped to SRM side and the RFC user should have authorization to use these data in SRM side.
BR,
Ivy