Service Completion Certificate Request from Supplier before Creating Service Entry Sheet.

Saksham_11
Participant
0 Kudos
412

Hi Team,

In the case of Service POs & as per the business process the supplier needs to request for "Service Completion certificate" & once the certificate has been approved & given to the supplier only after that the supplier can create SES & proceed further.

Is there any possibility in DSN to accommodate this as an additional task in the Service Scenarios?

Accepted Solutions (0)

Answers (1)

Answers (1)

Prem_Tracz
Product and Topic Expert
Product and Topic Expert

you cannot make it as a task.

you can have a custom field on SES creation that will be a mandatory question:

" Is your certificate for Service Completion approved? " YES/NO

in case supplier selects 'NO' - then SES cannot be submits as it throws an error message.

Saksham_11
Participant
0 Kudos

Hello Prem,

Thanks for the response.

Can I proceed further & raise a request with dsn4partners@sap.com for the same?