on 2020 Nov 03 3:11 PM
Hello All,
Scenario- Goods receipt extraction from SAP ECC towards SAP Ariba using CIG.
We have implemented CIG recently for sending messages to SAP Ariba. When we post goods receipt for multiple PO in single material document we are getting below error.
How to make above scenario working for multiple PO GR in single material document.In case of GR for single PO is successful.
Thank you,SanjayRequest clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.