on 2020 Jul 28 3:07 PM
Hi SMEs,
We have set up S/4 HANA Central Contract scenario in S/4 HANA 1809(On-Prem) setup with connected back end of ECC EHP 8.0 version
Steps we are using are as follows:
1) Creation of Central Contract in Hub system using Manage Central Purchase Contract app
2) Contract was created and approved in Hub system
3) XML message for Central contract- PurchaseContractDistributionReplicationRequest_Out is in success status
4) Central contract still showing the status as " In Distribution" in Hub system
5) We are able to see the PurchaseContractDistributionReplicationRequest_In as a successful message in the ECC back end via SRT_MONI
6) PurchaseContractDistributionConfirmationrequest_Out from ECC back end is also in sucessfull status
7) Contract is not replicated in the ECC system from Hub.
😎 Although XML messages in the Hub and Connected ECC systems are in Successful status but we are able to see the error description as follows in the message IDs.
System message: CL_API_MASTER_CONDITION_MM=>PROCESS
System message:No instance of object type PurchasingContract has been created. External reference: # 1
Please find error description details in the attachment.
9) FYI- Central Requisition and Central Purchasing scenarios are sucessfully working in our setup.
Thanks,
Nagesh S
Request clarification before answering.
Hi Pavan,
Incase the condition types between Hub & connected systems are different, there is provision to map the condition types of both the systems. And while distributing contracts to respective connected system it will read this customisation & create the local contracts with the condition types available in respective connected system.
You can find this customisation in SPRO under Central Procurement - Setting in Hub Systems, node
Regards
Anupam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nagesh,
Kindly check if mapping of pricing conditions between Hub & connected system is maintained in the customization
Regards
Anupam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nagesh,
Kindly check if mapping of pricing conditions between Hub & connected system is maintained in the customization
Regards
Anupam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Jayababu,
Refer this link. It contains configuration set up guides and business process flow information that you can use to implement the solution
https://community.sap.com/topics/s4hana-central-procurement.
Kr,
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nagesh
Good evening
I am Jayababu, I am searching for central procurement configuration since long but not proper information found , so please provide documentation if you have
Jayababu1010@gmail.com
Jaya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Somesh,
Thanks for your reply.
Please find attachment details as requested.
Data is maintained in both Hub and connected systems.
We have checked details from following transactions
Thanks,
Nagesh S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nagesh,
The issue seems to be due to inconsistent data , did you check central procurement operations monitor app? Also you can check gateway error log and AIF error log for more details.
Also check if you have maintained below data in both the systems:
Could you please share details in those logs also?
Regards,
Somesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.