R/3 to SRM Document type for determined back-end system missing

former_member507
Participant
0 Kudos
1,492

Where are in SRM

while transferring the PR from ECC to SRM im getting the error document type for determining back-end system missing


please see the below screenshot


Thanks

Saikrishna

View Entire Topic
ivy_li
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi sai,

from org structure, I could not figure out any problem, and it seems fine.

You may test with EXTR first. If it is working well, then the problem is your Z-document type.

BR,

Ivy

0 Kudos

Hi

Lvy Li,

Thanks for the reply!!

Thanks for spending valuable time and correcting the issue...

Thanks

Sai

0 Kudos

Hi

Lvy Li,

Now EXTR is comming fine actually we need to maintaintain DP_PROC_TY on Purchasing group "O"

Then only the external transfer will happen.

Thanks

SAI