Dear all,
When I copied a new RFx type and create one RFx manually, the delivery date in item is unable.I check the RFx transaction type and it seems ok.
Is there anyone met this problem? And any suggestions is appreciated.
Best regards,
weicheng
it's solved~
from note 2086521:
PATH:
-> SPRO
-> SRM Server
-> Cross-Application Basic Settings
-> Define Transaction Types
- Select the RFx BUS2200 and click on "Transaction types" structure.
- Double click the RFx transaction type that you use.
- Under "Process Control" in case flag is only set to "Contract" and not "Purchase order", system will grey out the field "Delivery Date".
- Reason is because "Delivery date" field is irrelevant for contracts and hence it is disabled.