Quantity cannot exceed the quantity XXXX.XX already calculated (item1)

Former Member
0 Likes
1,979

Hi ,

While uplifting a PO in SRM I am getting this error ''Quantity cannot exceed the quantity 10707.500 already calculated (item1)''  , This error is coming up while clicking on 'ORDER' button and not while clicking on 'CHECK' button , we are in extended classic.

Has any expert have exact idea about this error message.

Thanks

Sudhir

View Entire Topic
former_member208675
Active Contributor
0 Likes

Hi,

Are you able to create PO with lesser quantity?


Are you using WBS elements or internal order as account assignment?


Regards,

Former Member
0 Likes

Hi Vinay,

Thanks we are able to order the PO for the initial and less amount for which it was originaly ordered and even if we are increasing the quantity of line item 2  and keeping the quantity of line item-1 as it is, its Ordering the PO , but giving the error if we are increasing even for a very small qnty of line item -1.

We are using WBS element as accn asst.

and we are in ECS SRM 5.0 level 19

Thanks

Sudhir

former_member208675
Active Contributor
0 Likes

Hi,

Are you extending the value defined for WBS element (e.g. can be Internal Order)?

Regards,

Former Member
0 Likes

Hi Vinay,

Yes we are extending the Value of This PO , Any Help??.

Thanks

Sudhir

former_member208675
Active Contributor
0 Likes

Hi,

I wanted to know if in case if you'r extending value of WBS element?

You need to check it with FI consutlant the limits of the same.


Regards,

Former Member
0 Likes

Hi Vinay,

you mean if its showing limitations to budget like budget is not there , is it??

Thanks

Sudhir

former_member208675
Active Contributor
0 Likes

Hi,

Yes. I was on thinking on that path, but it should not be the case.

& just one thing, if you are creating PO with the contract reference, can you check the quantity limits?

Regards,

Former Member
0 Likes

Hi Vinay,

WBS is perfect because for same WBS element for line item no 2 its accepting the uplift ,the case is happening for line item 1 also this PO is not created with refference of any contract.

Thanks

Sudhir

Former Member
0 Likes

Hi Vinay,

WBS is perfect because for same WBS element for line item no 2 its accepting the uplift ,the case is happening for line item 1 also this PO is not created with refference of any contract.

Thanks

Sudhir

Former Member
0 Likes

Hi Vinay,

only one thing i am finding strange is below , I am not sure if i am right or not:

PO qnty is for line item 1 -> 200 days, for line item 2 its 10,000.00 days

confirmation for line item 1 is posted upto 193 days but service entry is showing 5,446 days.

same in line item 2 confirmation is posted for 9,992 days and entry sheet is created 10,097 days in SRM.

but in ECC every data is coming in sync.

so you find any sense in this , is it ok or something is wrong.

Thanks

Sudhir