on 2016 May 31 5:50 AM
Hi Gurus,
We are using SAP SRM 7.02 and ECC 6.04 in classic scenario. Process flow is like :- PR is created in Back end system and is converted to RFx in sap srm system via CPPR process.
Once RFx is created it gets updated in table Eban_tech but where does PR from Back end system gets updated in SAP SRM.
PLEASE NOTE THAT PR HERE IS NOT FOLLOW ON DOCUMENT.
Regards
Azad Mahato
Request clarification before answering.
Hello Azad,
PR is not stored in SRM system in any table. System uses eSOA services to transfer PR data to-and-fro b/w SRM and ECC. BADi ME_REQ_SOURCING_CUST is activated along with other settings to make CPPR work.
Refer note 1263876.
Regards,
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check trx bbp_pd for this RFx, and it should have linkage with previous document PR.
BR,
Ivy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Azad,
Please check back end tables.
BBP_PDBEH Backend Specific Header Data
BBP_PDBEI Backend Specific Item Data
Regards,
Venkat