on 2010 Oct 29 9:11 PM
Hi Maters of SRM
when I create the confirmation into SRM/EBP when IDOC is sended to Backend MBGMCR the confirmation is created in Backend so far so good , but after into WE02 into Backend show me an error message
PU Ordered quantity excedido en 1 052 : 8907 CPAP where 052 will be PZA=EA 8607 material item and CPAP plant
what can I do to fix that error.
Thanks for your attention.
Request clarification before answering.
the problem is tolerance in Backend, I was modificated the tolerance in transaction OMCO without check tolerance and the error disaper.
thanks