Hi SAP experts,
We are in SRM 7 with ECC 6 (no EHP). We notice something strange in our testing. Let's say we create SC with qty = 10 pcs. Then we create RFx for vendor A and vendor B. We decide that BOTH of them win. Then we create PO from RFx to vendor A with qty = 10 pcs, and then we create another PO from RFx to vendor B with qty = 10 pcs. The second PO can be ordered regardless that the PO qty is greater than SC qty.
Is there any setting to prevent this?
Best regards,
John
Request clarification before answering.
Hi,
This is standard behaviour where you can create mutiple follow on documents of same kind say PO or contract from a Rfx response.
Regards
sam