on 2015 Apr 02 4:53 PM
Hello,
SRM : EHP3 713
ECC : EHP 7 ERP 6
Iam setting up SRM system for a Classic scenario and iam getting the following issue.
After SC approval - PR is getting created in the backend if there is no fixed vendor which is fine , but in case for SC's where Fixed vendor is there and once the SC is approved the status shows that Item transfer in Process for long time and nothing happens.
I have tried to push the SC using the FM : BBP_PD_SC_TRANSFER and iam getting a runtime error stating that ASSERTION FAILED.
Any light on this issue would be highly appreciated.
Regards
Sudhakar