on 2010 Jun 07 2:40 AM
Hi,
I create a PO according to contract in SRM 7.0 ECS, but in ECC , I found the Po haven't contract information. I don't know why contract can't transfer to ECC , the contract exist in both ECC and SRM.
Please tell me reason.
thanks
Jesse
Request clarification before answering.
Hi
give us more detail.
What type of contract you assigned in the sc?
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you see your contract document flow SRM system and find the PO?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
In the SRM system the leading PO is already assigned as a release order
of the central contract, the backend PO is only a copy of the SRM PO.
As a result in this copy of the PO the contract is not overtaken in the
table EKPO.
So in conclusion when using the Extended Classic scenario the contract
details that is within the PO in SRM is not sent over to the R/3
copy of the PO.
One option would be to use the BBP_ECS_PO_OUT_BADI and map custom
fields to the backend transfering the contract number to a field in
the R/3 PO.
Thanks and regards
Summer Wang
hi
In the SRM system the leading PO is already assigned as a release order
of the central contract, the backend PO is only a copy of the SRM PO.
As a result in this copy of the PO the contract is not overtaken in the
table EKPO.
So in conclusion when using the Extended Classic scenario the contract
details that is within the PO in SRM is not sent over to the R/3
copy of the PO.
One option would be to use the BBP_ECS_PO_OUT_BADI and map custom
fields to the backend transfering the contract number to a field in
the R/3 PO.
Thanks and regards
Summer Wang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.