Hi,

I create a PO according to contract in SRM 7.0 ECS, but in ECC , I found the Po haven't contract information. I don't know why contract can't transfer to ECC , the contract exist in both ECC and SRM.

Please tell me reason.

thanks

Jesse

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Likes

Hi

give us more detail.

What type of contract you assigned in the sc?

Muthu

former_member324993
Active Contributor
0 Likes

Did you see your contract document flow SRM system and find the PO?

summer_wang1
Product and Topic Expert
Product and Topic Expert
0 Likes

hi

In the SRM system the leading PO is already assigned as a release order

of the central contract, the backend PO is only a copy of the SRM PO.

As a result in this copy of the PO the contract is not overtaken in the

table EKPO.

So in conclusion when using the Extended Classic scenario the contract

details that is within the PO in SRM is not sent over to the R/3

copy of the PO.

One option would be to use the BBP_ECS_PO_OUT_BADI and map custom

fields to the backend transfering the contract number to a field in

the R/3 PO.

Thanks and regards

Summer Wang

summer_wang1
Product and Topic Expert
Product and Topic Expert
0 Likes

hi

In the SRM system the leading PO is already assigned as a release order

of the central contract, the backend PO is only a copy of the SRM PO.

As a result in this copy of the PO the contract is not overtaken in the

table EKPO.

So in conclusion when using the Extended Classic scenario the contract

details that is within the PO in SRM is not sent over to the R/3

copy of the PO.

One option would be to use the BBP_ECS_PO_OUT_BADI and map custom

fields to the backend transfering the contract number to a field in

the R/3 PO.

Thanks and regards

Summer Wang