Hi guru,

i have to implement the business scenario Plan Driven Procurement in SRM 7.0. I want to transfer purchase requsitions from SAP back end in sourcing cockpit. Could you please tell me the steps to implement? In a specific way, Is it mandatory for this scenario to replicate the products from back end (throught report Material) ?

Thanks in advance.

L.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes
Former Member
0 Likes

Thanks a lot!!!

I read that for the customizing of Plan Driven it is necessary the customizing of all steps of direct material ( Self-Service Procurement of Direct Material 😞 to replicate units, product categories,and material types and the necessary products from the back ends.

Could you please clarify this statement?

Best Regards

L.

Former Member
0 Likes

Hi,

The Material created in the ECC 6.0 is PR . This is getting pushed to SRM

In SRM -you are procuring the Direct material (Plan Driven Procurement) .PR will be in Sourcing Cockpit

create a shopping cart and other process follow.

G.Ganesh Kumar

Former Member
0 Likes

Thank yuo Gopinatha rao,

a last question: in which scenario is mandatory to transfer from ECC to SRM the material master record (throught R3AS)?

Best Regards

L.

Former Member
0 Likes

Hi,

If the business uses only Indirect purchasing then Self Service Procurement (classis (or) Extended classic) is sufficient

If the business requires that shopping cart will be created for Direct Material ((plan Driven Procurement) then you have to

replicate theMaterial Master from thro middleware .

Requistion can be pushed from ECC .(or) some other system like SAP APO to SRM

Regards

G.Ganesh Kumar

Former Member
0 Likes

Hi

There are 4 points regarding replicaton of produt master. As it is mentioned above ,

1. if you are going to user directl procurement (Extended classic) scenario you need to replicate locations (Plant) & Product master into SRM.

2. In case if you are managing contracts in SRM and replicating to ECC (either srm 7.0 / 5.0 versions) then you need to replicate product master to SRM in order to create GOA / Central contractrs against a prodcut

3. If your implementation is decoupled scenario (Classic + Ext.classic), and you want to create reservations in ECC through SRM then you need to replicate products into SRM

4. Finally, when your implementation scenario is Classic then if you user SRM for stock procuremnent / reservations creations from SRM then you need to replicate product master to SRM.

Hope this will give you more clarity on your query.