PDP: How to transfer PR manually?

Former Member
0 Likes
184

Dear expert,

I met an issue that , in PDP, if the PR transfer failed, I need to transfer the PR again.

Until now, I have only the resolution that enter an PR manually into table EPRTRANS and run report BBP_EXTREQ_TRANSFER manually.

The reason why I do this is because the PR was approved and custom doesnot want to change the PR any more.

But I have to make effort to enter an PR manually into table EPRTRANS.

Is there any better way to do this?

Regards,

Hayashi.

Accepted Solutions (0)

Answers (1)

Answers (1)

ivy_li
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Hayashi,

I am afraid that when PR transfer failed, the entry in table EPRTRANS will be removed. And you have to fix the exact error and then delete the stuck queue in trx smq1, and make some changes to this PR in order to generate one entry in EPRTRANS. Then transfer is possible again.

This is standard system design which is hard-coded, so you can only change this logic by modifying standard coding.

Maybe you can consider using SOA to transfer PR instead of using report.

Regards,