on 2012 May 03 4:49 PM
Hi All ,
Extended classic scenario , SRM 5.0 , ECC 5.0
Consider the following scenario :
PO created in SRM and ordered -> GR done fully -> PO changed and quantity increased in the PO and PO ordered -> Now if you go the change mode of the PO , the goods recepient field is greyed out. The deletion button for the goods recepient is also inactive. There is no way to change the goods recepient
Please let me know if there is any SAP notes for this ?
Regards,
Saurav Agarwal
Request clarification before answering.
Hello Saurav,
as initial quantity for item PO was already confirmed, it is not possible to change goods recipient.
I assume if item quantity was not already confirmed, you should have been authorized to change goods recipient for this item.
Two solutions:
Regards.
Laurent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Laurent. ,
Thanks for the reply . But is this a standard functionality ? There could be quite a few POs whose quanity might have been increased after it has been fully receipted . So , in case the goods recipient leaves the organization , is there no way to change the PO goods recipient ? Changing the GR person is necessary because our invoice block workflow are sent to the GR persons.
Please advise.
Regards,
Saurav Agarwal
Hello,
saurav . wrote:
(...)
Thanks for the reply . But is this a standard functionality ?
(...)I think so.
saurav . wrote:
(...)
So , in case the goods recipient leaves the organization , is there no way to change the PO goods recipient ?
(...)
There is no standard way, so you can:
Regards.
Laurent.