Multiple lines with Planned and Unplanned items issue - only 1st line item has a SES in SAP ECC

janinaflorian
Participant
329

Hi Experts,

We have a scenario where there are 2 service PO line items, one is planned (service tab in SAP ECC) and another is unplanned (limits tab in SAP ECC). Now when we create Service Sheet in Ariba Network, it is allowing us to create for both lines (meaning planned and unplanned) but in ECC only the 1st line item has a SES created and not the 2nd line item. Please advise on what we can do on this. Thank you!

Accepted Solutions (0)

Answers (1)

Answers (1)

Prem_Tracz
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Janina,

This is not supported scenario for SAP ERP.

It works for other ERP systems so that is why it is allowed on Ariba Network.

Best practice is to only create POs with planned or only unplanned items.

sheenaelava
Explorer
0 Kudos

Hi Prem,

Can you please advise if multiple unplanned items can be created/submitted in one SES document? I tried submitting SES with 2 unplanned (limits) lines but encountered an error in SAP ECC stating "Service line 2: no overall limit for unpl. services amounting to "xxxx" exists. Thank you!