on 2012 Mar 08 5:28 AM
Hello Experts,
We are facing the below issue,
We are trying to create Limit SC with MAA cost center with cost distribution "By Value". we distribute the total value to 5 cost centers. when we try to order the SC, system is not allowing us to order, we got the error message "Multiple account assignment only with percentage less than 100%".
Please advise how to resolve this issue.
Regards,
Santhosh Kumar.G
Request clarification before answering.
Hi
Check this OSS notes : 1644804
Regards
G.Ganesh Kumar