on 2012 Apr 12 2:14 PM
Hi Guys!
I'm tryng to find somewhere how can I determine the backend, I mean how the stardard works with.
Cause here the Company Code is the same in 4 differentes backends, same for Purchase Organization.
Other stardard ways to determine the backend system??
(First Time with Multi Backend)
Thanks in advance!!!
Gax
Request clarification before answering.
Hi,
The standards way to determine follow-on document creation in the back end system is based on your configuration in SRM
under:
SPRO > IMG > SAP Supplier Relationship Management > SRM Server > Cross-Application Basic Settings > Define Objects in Backend System (Purch. Reqs, Reservations, Purch. Orders)
Here you can define per logical system i.e. Source system.
You can also use the BADI > BBP_TARGET_OBJTYPE if you wish to implement a different logic for creating documents in the backend system.
Thanks,
Hari