on 2012 Jul 26 6:00 AM
Dear Experts,
I am facing this issue when we the shopping cart is completely approved. I have gone through the sdn links but felt thats not helping.
Please find the details of my system.(SRM 7.0 and EHP5)-Classic Secnario
I am creating a free text item with material group T100 in SRM.
At R3 side.
I have an info record for the material group.
ECPO document type has item category B already maintained
At SRM side
in org Strcture i have maintained two document types in BSA attribute(not defaulted any thing)
ZNB--- for PR
ZCPO-- for PO
Define backend objects setting
* T100 Reserve generated if stock PO if item data complete if not PR.
i have define number ranges in SRM
PO 2000000000 2999999999
this is assigned to ZCPO transaction type
Same number range has been maintained as external and assigned to ZCPO in R3 under PO document types
similarly in SRM for PR number range is maintained
| PR | 3000000000 | 3999999999 |
this is assigned to ZNB in R3 system as external.
PR is getting created as defined in the sytem but PO is not getting created.
please let me know if i need to do any changes
Regards
Subha
Request clarification before answering.
Hi Malay,
I have checked in BBP_PD ,
BE_Object_ID is filled with the number range of PR
Document type is taken properly as ECPO only.
regards
Subha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please go through the link.
http://scn.sap.com/thread/1540525
Check if the document type in lower case may be the issue.
With Regards,
Malay
Hi Malay,
No i have maintained the document type from search help.
i will go through the link you have provided.Mean while i did the following
I have removed the document type ZCPO in BSA attribute and created a shopping cart with inforecord it has created PR
i went back and checked the shopping cart assign SOS , i didnt find the info record which was there when i ordered the shopping cart.
Regards
Subha
Hi Subhalakshmi,
For those cases where PR got generated & PO did not come through auto, Pl run ME59N in R/3 to check the incompletion data & action further..
Pl do let us know
BR/Ranganath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It may be due to incomplete data for creation of PO.
In ECC test system please try to create PO with those data you have during creation of SC and check if any missing data for PO creation.
While creating PO in ECC with document type ZCPO, you can manually enter external number for PO document (for ex 2000000100).
With Regards,
Malay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.