on 2016 Sep 11 7:35 PM
Request clarification before answering.
Hi Atul
Please Check all points as below
1. Please delete queues from SMQ1 and SMQ2 on both servers SRM and ECC.
2. In R3AM1, cancel failed object DNL_CUST_PROD1 and re run object in DNL_CUST_PROD1
3. Check Site setting (SMOEAC) both SRM and ECC are correctly defined there will be CRM instead of SRM which is fine also RFC Destinsation are working
try to remote login and check connections
4. You need to make sure that the following objects has been replicated successfully( Green Light should appear):
DNL_CUST_BASIS3 (units of measure, dimensions, and currencies)
DNL_CUST_PROD0 (product categories)
DNL_CUST_PROD1 (product categories)
5. Check all table entries are correct;y configured CRMCONSUM,CRMRFCPAR, CRMPAROLTP and others
Refer these links for middle ware configuration as well for a similar error which you are facing
http://scn.sap.com/community/crm/master-data-and-middleware/blog/2014/09/15/why-parent-not-ok
Regards
Vinita