on 2015 Oct 06 11:06 AM
Hello everyone,
i would like to have confirmation regarding a SRM standard process for Work Item generated by standard task 40107924 (review of PO).
This Work Item is generated when you manually add a reviewer (Ad Hoc reviewer).
This WI remains active until the PO workflow is completed: at this moment, the dialog WI is logically deleted.
What i find not logical is if reviewer "submits" his review, a new WI is generated, so reviewer will receive dunning mails to review the PO each time he will submit his review until the end of the PO workflow: this has no sense !
Once review is submitted, no new WI has to be generated.
So, is this process the SRM standard one?
I did not find any OSS notes dealing with this subject.
We are in SRM 7.00
Regards.
Laurent.
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hello,
one of my colleagues found the amazing answer....
1684003 - Review workitem created repeatedly
No comment.
Regards.
Laurent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Which process you are using
Are you working on Process controlled workflow? or Normal workflow.
Thanks
Nishant