on 2016 Jan 04 11:49 AM
Hello,
We work on SRM 7.02 ( Extended Classic Scenario ). We have implemented Planned Driven Procurement.
From last week we observed that - Purchase Requisitions from R/3 are getting failed while conversion to SC.
Below are the two error messages found in SLG1 ( SRM )
1)The system could not determine the "Ordering Party"
2)Supplier 000XXXXXXX not intended for purch. org. XXXXXXX Org. System is trying to assign Supplier from some different Purchasing Organization automatically.
We checked the RFC user assignment in SRM Organization structure , and everything seems to be fine.
Can somebody guide for this issue?
Thanks & Regards,
Pankaj
Hi Pankaj
Have you maintained the attributes of the user with company code and the entry channel for RFC user is mapped to the correct backend purchasing group ?.
regards
Vinita